Sanctuary Phase 1, Week 6
The storage space behind stage left of the stage in our Social Hall has been removed and is being prepared for the construction of two new accessible bathrooms. Brackets and support for the new Social Hall storage closets have been erected on either side of the Social Hall. The tracks for our new recessed Sanctuary lighting have been cut. The new Sanctuary lighting will increase visibility and enhance the beauty of our newly renovated Sanctuary.